Current Projects    - projects completed less than 5 years ago


Projects Filter

   ALL
   extreme, emergency and specialised works
   drill and blast
   quarrying and mining
   tunnelling
   ground and slope stabilisation
   civil bulk earthworks
   consulting
NX2 - Pūhoi to Warkworth, SH1
Date: 2017 - present
Client: Fletcher/Acciona
Project value: $9.8m
 

The Pūhoi to Warkworth project will extend the four-lane Northern Motorway (SH1) 18.5km from the Johnstone’s Hill Tunnels to just north of Warkworth. It is the first stage of the Ara Tūhono – Pūhoi to Wellsford Road of National Significance (RoNS). The extension is due to be open for traffic by late 2021. Geotech have been contracted to conduct all major earthworks as part of this project. Work is spread over three major work areas.

Kaikoura Tunnels
Date: 2017 - present
Client: NCTIR
Project value: In excess of $1m - ongoing
 
Project info: kaikoura-tunnels.pdf

The damage caused by the 7.8 magnitude November 2016 Kaikoura earthquake to the Main North Line (MNL) railway (and SH1 along the east coast of the South Island) was unprecedented in New Zealand. There were 60 major damage sites along the MNL, including tunnels, bridges and embankments. Geotech have had two tunnel crews and support staff providing tunnel remediation services.

Kaikoura Earthworks
Date: 2017 - present
Client: NCTIR
Project value: $5m ongoing
 

Geotech were engaged by the North Canterbury Transport Infrastructure Recovery(NCTIR)to assist with restoring road access to Kaikoura after the 7.8 magnitude earthquake in November 2016. Geotech staff have been working on sections of the narrow coastal corridor of SH1 south of Kaikoura, with additional crews working north of Kaikoura. Works have predominantly been made up of clearing landslides. Work is not straightforward due to the fractured cliff faces being unstable. Damaged slopes continue to release rock and material, and weather events and continuing seismic activity have presented ongoing challenges throughout the contract, including additional land and mud slides during bad weather events.

Avon River stopbank construction
Date: 2017 - 2018
Client: Christchurch City Council
Project value: $3.5m
 

Chatham Islands quarry management
Date: 2015 - 2017
Client: Southern Screenworks Ltd
Project value: $497k
 

Geotech were contracted to establish and operate a quarry on the Chatham Islands. The quarry was required to provide concrete aggregate for the Chatham Islands Wharf upgrade. The project required construction of a decant pond, establishment of a 26,000m2 quarry, establishment of a site office, construction of access roads, stockpile areas for overburden and material, quarry blasting, general quarry management, explosives management and design of rehabilitation.

Karamea Bluff dropout reinstatement
Date: 2015
Client: Buller District Council
Project value: $215k
 

Geotech were engaged as a subcontractor to complete slope stabilisation work below the State Highway to repair embankment slips and a substantial drop out, resulting from a severe weather event. A filled embankment (around 11m in height) was constructed using a terramesh system and geofabrics to bring the level back up to the road pavement level at the drop out site. Terrain was steep at the site, and access was difficult.

Maybille Bay hybrid fence
Date: 2015
Client: NZ Transport Agency
Project value: $149k
 

Geotech were engaged to install a hybrid catch fence to protect SH6 traffic from rockfall risk. The contracted works supplied included rockscaling and vegetation removal, drilling, grouting and testing, hybrid catch fence installation, traffic control, site rehabilitation, tidy up and demobilisation.

Robinsons Bay retaining wall
Date: 2015
Client: Opus
Project value: $396k
 

Geotech were awarded the tender to construct a shotcrete and soil nail retaining wall structure above State Highway 75 between Duvauchelle and Robinson’s Bay. The contracted works supplied included,construction of access to the work area and vegetation clearance; Excavation of a working platform; Construction of a shotcrete and soil nail retaining wall; Carpentry works, including construction of wooden stairs and hand rails; Installation of elevated stormwater and sewage pipe lines suspended from the wall face; Landscaping; Compaction of soils; Site rehabilitation, tidy up and demobilisation.

Rockmilling - Ferry Bluff, Hanmer
Date: 2015
Client: NZTA / Opus
Project value: $27k
 

Geotech were engaged as a subcontractor to undertake rock removal at SH7A, Ferry Cutting. The rock to be removed was overhanging the road and falling, creating a dangerous hazard that could not be removed conventionally. The site was just past a narrow bridge, on a two lane stretch of road, with embankments on each side. A minimum of road closure disruption was required by the client, as the road leads into a high profile tourist town (Hanmer Springs). Geotech proposed a methodology utilising mass blocks to assist with ramping an excavator up to the required height, and milling the rock using an Erkat milling head. The option offered a high level of precision without the risk of additional damage to an existing poor rock mass that was actively failing. It also meant that staff were protected from any rockfall risk, and single lane access for traffic was able to be maintained for the majority of the contract works.

Banbury heritage restoration project
Date: 2013 - 2014
Client: Department of Conservation
Project value: $300k
 

Operational from 1879 to 1890, the Banbury Mine was the first producing mine on the Denniston plateau. An underground coal mine, Banbury is now part of the high profile mining heritage site at Denniston. In 2008, the Department of Conservation, in conjunction with the Denniston Heritage Charitable Trust, undertook a project with a view to re-opening parts of the mine and tram line for a tourist heritage operation, now operational as the ‘Denniston Experience’. Geotech were engaged to assist in the establishment of a 179m second egress for the Denniston Experience, running from the mine to the surface.

Strongman Open Cut Mine
Date: 2010 - 2015
Client: Solid Energy New Zealand Ltd
Project value: $30.5m
 

Geotech ran Strongman Mine on behalf of Solid Energy New Zealand based around a methodology of how to gain additional resource from the depleted and finished mine, this was done by using precision blasting to steepen up pit highwalls enabling extraction of the exposed coal. Geotech was responsible for funding, fleet configuration and maintenance, mine planning, resource assessment and extraction/production planning, that was completed over five years with 34 fulltime staff on site.

 

Head Office

State Highway 6
Charleston
West Coast 7730
Phone: 03 280 8603